For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity

Question:

For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and calculate the project duration. Then draw a time-scaled network and under it a labor resource histogram for the ES. Do the same for the LS. In both cases, use the maximum allowable number of workers. Finally, make adjustments to the noncritical activities, within the constraints of the ES and LF and the maximum and minimum workers allowed to provide what you feel is the best labor distribution.

What do you feel is the biggest problem with the ES and LS configurations, and how has this been alleviated with your solution?


Predecessor
WorkersAllowed
ActivityRelationshipsDurationMaximumMinimum
A
333
BA: FS433
CA: FS342
DA: FS484
EB: FS455
FB,C: FS532
GE, F: FS622
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Project Management

ISBN: 9781118745052

6th Edition

Authors: S. Keoki Sears, Glenn A. Sears, Richard H. Clough, Jerald L. Rounds, Robert O. Segner

Question Posted: