For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity

Question:

For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical calculation to shorten the project activity by activity in a least-cost manner. What isthe total cost of the crashed project? Why is this less than the sum of the crashed costs for the seven activities?

ActivityRelationshipsNormal DurationCrash DurationNormal CostCrash Cost
A
32$$ 3,000$$$ 3,150$
BA: FS43$$ 4,000$$$ 4,250$
CB: FS31$$ 6,500$$$ 7,000$
DA: FS42$$ 6,000$$$ 6,500$
ED: FS42$$ 3,500$$$ 3,900$
FA: FS52$$ 2,200$$$ 2,725$
GC, E, F: FS64$$ 3,900$$$ 5,000$
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Project Management

ISBN: 9781118745052

6th Edition

Authors: S. Keoki Sears, Glenn A. Sears, Richard H. Clough, Jerald L. Rounds, Robert O. Segner

Question Posted: