Given the following diagrams of progress on individual work packages of a project answer the following questions:
Question:
Given the following diagrams of progress on individual work packages of a project answer the following questions:
a. For Case 1, is the project ahead or behind schedule?
b. For Case 2, is the project over or under budget?
c. For Case 3, is the CPI greater than 1?
d. For Case 1, is the SPI greater than 1? Explain by calculation.
e. For Case 4, is the project on schedule and budget? Explain.