Given the immediate predecessors and a, m, b for each activity in the tables below, compute: a.
Question:
Given the immediate predecessors and
a, m, b for each activity in the tables below, compute:
a. te and V for each activity
b. ES, EF, LS, and LF for each activity.
c. Te and Vp for the project.