Project A and Project B both have the same overall cost of $4M. Project As likelihood of

Question:

Project A and Project B both have the same overall cost of $4M. Project A’s likelihood of success is 95 percent, B’s chances are 50 percent. Project A is expected to generate $11M but will incur $5M maintenance in costs. Project B is expected to generate revenue of $8M and also to provide increased effi ciencies that would save

$5M in expenses. Applying the B/C ratio, which project would you recommend?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: