Projects W, X, Y, and Z are each being screened according to four criteria: Potential Return on
Question:
Projects W, X, Y, and Z are each being screened according to four criteria:
Potential Return on Investment, Lack of Technological Risk, Environmental
“Friendliness,” and Service to Community:
• Project W: Return, high; Risk, medium; Environment, medium; Service, low
• Project X: Return, medium; Risk, high; Environment, medium; Service, low
• Project Y: Return, medium; Risk, medium; Environment, high; Service, high
• Project Z: Return, medium; Risk, medium; Environment, high; Service, low.
Create a scheme for screening the projects, assuming equal weight for all criteria.
Which project comes out best; which worst?