Refer to the fi rst network in the above problem. a. What is P(Te < 23)? b.
Question:
Refer to the fi rst network in the above problem.
a. What is P(Te < 23)?
b. What is P(Te < 32)?
c. For what Ts is the probability 95 percent that the project will be completed?