Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC,
Question:
Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC, TS, CRD, and ACTIM. What is the shortest project duration obtained?
Which heuristics yield that shortest project duration?