Suppose in Figure 6.20 everything is the same except Activity Y can start 4 days after Activity
Question:
Suppose in Figure 6.20 everything is the same except Activity Y can start 4 days after Activity V starts, but cannot be fi nished until 6 days after Activity V is fi nished. Show how this changes the values for ES, EF, LS, and LF.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management For Engineering Business And Technology
ISBN: 9780080967042
4th Edition
Authors: John M. Nicholas, Herman Steyn
Question Posted: