Suppose it is known that the duration of a project has a triangular distribution with a lower
Question:
Suppose it is known that the duration of a project has a triangular distribution with a lower limit of 24 months, an upper limit of 46 months, and a mode of 36 months. Find the probability that the project can be completed in 40 months or less.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 9781420083200
1st Edition
Authors: Adedeji B Badiru
Question Posted: