Suppose it is known that the duration of a project has a triangular distribution with a lower

Question:

Suppose it is known that the duration of a project has a triangular distribution with a lower limit of 24 months, an upper limit of 46 months, and a mode of 36 months. Find the probability that the project can be completed in 40 months or less.