The contractor on a lump-sum contract invoiced for 80 percent of the work, but the architect feels
Question:
The contractor on a lump-sum contract invoiced for 80 percent of the work, but the architect feels that there is actually about 30 percent more work to be done, not 20 percent. What is the architect's likely response to the contractor's payment application?