The diagram below was drawn before it became clear that Mary would have to perform both Activity
Question:
The diagram below was drawn before it became clear that Mary would have to perform both Activity B and Activity F.
a. With the realization that Mary has to do the two tasks, indicate two possible critical chains.
b. Reschedule the work and indicate the position and the size of the feeding buffer.