The equivalent of cost reimbursable contracts is frequently termed: a. Back charge contracts. b. Fixed price contracts.
Question:
The equivalent of cost reimbursable contracts is frequently termed:
a. Back charge contracts.
b. Fixed price contracts.
c. Progress payment contracts.
d. Cost plus contracts.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Preparing For The Project Management Professional (PMP Certification Exam)
ISBN: 9780814471722
2nd Edition
Authors: Michael W. Newell PMP ENP
Question Posted: