The following CPM network is subject to the following two simultaneous restrictions: a. The project cannot start
Question:
The following CPM network is subject to the following two simultaneous restrictions:
a. The project cannot start until 5days from time 0 (i.e., ES of the start node = 5).
b. There is a deadline of 35days (i.e., LC of the finish node = 35). Perform the forward and backward CPM computations and show ES, LS, EC, LC, TS, and FS for each activity. What is the TS for each activity on the critical path?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted: