The following CPM network is subject to the following two simultaneous restrictions: a. The project cannot start

Question:

The following CPM network is subject to the following two simultaneous restrictions:

a. The project cannot start until 5days from time 0 (i.e., ES of the start node = 5).

b. There is a deadline of 35days (i.e., LC of the finish node = 35). Perform the forward and backward CPM computations and show ES, LS, EC, LC, TS, and FS for each activity. What is the TS for each activity on the critical path?