The project team has delivered a deliverable to the customer. The deliverable contains defects that are easily

Question:

The project team has delivered a deliverable to the customer. The deliverable contains defects that are easily correctable. There is a good relationship with the customer and the customer agrees to make the repairs and correct the defects on the item and invoice the supplier for the work that was done. This is considered to be a:

a. Bid cost reduction.

b. Payment authorization.

c. Back charge.

d. Release payment.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: