Three resource types (RES 1, RES 2, and RES 3) are to be assigned to a certain

Question:

Three resource types (RES 1, RES 2, and RES 3) are to be assigned to a certain task. RES 1 working alone can complete the task in 35 days, RES 2 working alone can complete the task in 40 days, and RES 3 working alone can complete the task in 60 days. Suppose 1 unit of RES 1 and 1 unit of RES 2 start working on the task together at time 0 . Two units of RES 3 are brought in to join the task sometime after time 0 . RES 2 quits the task when there is \(20 \%\) of the task remaining. If the full task is desired to be completed 13 days from time 0 , determine how many days from time 0 the 2 units of RES 3 should be brought in to join the task. Assume that work rates are constant and units of the same resource type have equal work rates.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: