Use the computational measure presented in this chapter to compute the resource utilization level (area) for each
Question:
Use the computational measure presented in this chapter to compute the resource utilization level (area) for each schedule in Exercise 5.6.
Exercise 5.6
Schedule the project in Exercise 5.3 using each of the following heuristics: CAF, LS, ES, LC, EC, TS, CRD, and ACTIM. What is the shortest project duration obtained? Which heuristics yield that shortest project duration?
Exercise 5.3
Use the minimum totals lack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Units of resource type 1 available \(=10\)
Units of resource type 2 available \(=15\)