You are a project manager for Community Trends, a nonprofit organization. Your project has come about because

Question:

You are a project manager for Community Trends, a nonprofit organization. Your project has come about because of a social need. You’re calculating performance measurements and using actual costs to date, and you assume that ETC work will be completed at the budgeted rate. You know the following information: BAC = 900, ETC = 65, PV = 500, EV = 475, and AC =