You are given the following information about a dry-batch paving operation. You are going to use one

Question:

You are given the following information about a dry-batch paving operation. You are going to use one mixer that has a service rate of 30 services per hour. The dry-batch trucks you use for bringing concrete to the paver have an arrival rate of 7.5 arrivals per hour. Each truck carries 6 cubic yards of concrete. You have a total amount of 13,500 cubic yards of concrete to pour. You rent a truck at $15 per hour and the paver at $60 per hour. If the job takes more than 80 hours, you pay a penalty of $140 per hour owing to delays in job completion. On the basis of least cost, determine the number of trucks you should use. Plot the cost versus the number of trucks used.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Management

ISBN: 9781119256809

5th Edition

Authors: Daniel W. Halpin, Bolivar A. Senior, Gunnar Lucko

Question Posted: