A Gantt chart represents project schedule information in an easy-to-read, graphical format. Which of these is not

Question:

A Gantt chart represents project schedule information in an easy-to-read, graphical format.

Which of these is not a component of this type of Gantt chart?

a. activities

b. budget data

c. start and end dates

d. durations