As a project manager, which of the following situations would concern you the most? a. a three-day
Question:
As a project manager, which of the following situations would concern you the most?
a. a three-day delay on an activity with five days total float
b. realizing that an activity on your critical path only took two days instead of the four you assigned it using the PERT method
c. a one-day delay to an activity with zero total float
d. a two-day delay to a non-critical path activity with two predecessor activities