Crashing the following activity chains would save time and cost extra money as follows: AGJQ2 days $300

Question:

Crashing the following activity chains would save time and cost extra money as follows:

AGJQ—2 days $300 CDIL—3 days $400 Which sequence of activities would you, as a project manager, choose to crash?

a. AGJQ

b. CDIL

c. neither AGJQ nor CDIL

d. depends on which, if either, is on the critical path