During which project management process would a company auditor verify that all contracts have been completed and
Question:
During which project management process would a company auditor verify that all contracts have been completed and all required purchasing standards and methodologies have been followed for the project?
a. Validate scope
b. Close contracts
c. Close project or phase
d. Conduct procurements