Good project management practice suggests a need to include a _______________ within the cost baseline in order

Question:

Good project management practice suggests a need to include a _______________ within the cost baseline in order to cover identified risks that are accepted, and for which responses have been developed.

a. contingency reserve

b. project buffer

c. control account

d. management reserve