Eyring Manufacturing produces a component used in its production of washing machines. The time to set up
Question:
Eyring Manufacturing produces a component used in its production of washing machines. The time to set up and produce a batch of the components is two days. The average daily usage is 800 components, and the maximum daily usage is 875 components.
Required:
Compute the reorder point assuming that safety stock is carried by Eyring Manufacturing.
How much safety stock is carried by Eyring?LO1