Safety Stock; Order Point. Eagle Companys usage of Material A is 9,600 units during 240 working days
Question:
Safety Stock; Order Point. Eagle Company’s usage of Material A is 9,600 units during 240 working days per year. Normal lead time and maximum lead time are 20 working days and 30 working days, respectively.
Required: Assuming Material A will be required evenly throughout the year, what is the safety stock and order point?
LO2