A worker is allowed 18 hours to complete a job, which he accomplishes in 12 hours. His

Question:

A worker is allowed 18 hours to complete a job, which he accomplishes in 12 hours. His hourly rate is Rs. 2.

The material cost of the product is Rs. 20. The overheads are recovered at 75% of the direct wages. Calculate the factory cost of the job under

(a) piece rate,

(b) Halsey plan, and

(c) Rowan plan.