Completing a job cost sheet. The partially completed job cost sheet prepared at the Ortega Manufacturing Company

Question:

Completing a job cost sheet. The partially completed job cost sheet prepared at the Ortega Manufacturing Company for Job 4-09 is given below. (This sheet is reproduced in the Study Guide and Working Papers. If you are using the workbook, do all of the following activities there.)

image text in transcribed

Instructions 1. Compute and enter the departmental direct labor costs on the job cost sheet for Job 4-09. The labor rates are as follows: Cutting Department, $4.60 per hour;
Sewing Department, $5.25 per hour; and Finishing Department, $4.30 per hour.
2. The Ortega Manufacturing Company applies overhead to work in process on the basis of direct labor hours. Use the overhead application rates given below to determine the manufacturing overhead to be applied to each department. Record the applied overhead on the job cost sheet for Job 4-09.
Cutting Department $8.25 per direct labor hour Sewing Department 6.42 per direct labor hour Finishing Department 9.20 per direct labor hour 3. Total all columns and draw a double rule. Complete the Summary and Total Cost sections of the job cost sheet for Job 4-09.

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: