JIT and cost control Matsui Industries produces 10,000 units each day and the average number of units

Question:

JIT and cost control Matsui Industries produces 10,000 units each day and the average number of units in work in process is 40,000.

1. Determine the throughput time.
2. If the same daily output can be achieved while reducing the work in process by 60%, determine the new throughput time.