Show Glow, Inc., has signed a contract with the More Poor Corp. to design an apartment complex
Question:
Show Glow, Inc., has signed a contract with the More Poor Corp. to design an apartment complex and construct the buildings within. The following data was collected by the engineers: mk69
Assume activities A and B begin at the same event and activities P and Q are completed at the same event.
Required:
a Develop the PERT network. Include the duration of each activity in your diagram.
b Determine the following:
1 The earliest expected completion time for each event 2 The latest allowable time for each event 3. The slack time for each event c Determine the total cost of completing the critical path.