The labour budget of a company for a week is as follows: 20 skilled men at Rs.

Question:

The labour budget of a company for a week is as follows:

20 skilled men at Rs. 5 per hour for 40 hours.

40 unskilled men at Rs. 3 per hour for 40 hours.

The actual employment was as follows:

30 skilled men at Rs. 5 per hour for 40 hours.

30 unskilled men at Rs. 4 per hour for 40 hours.

Calculate labour variances.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting

ISBN: 9788131732076

1st Edition

Authors: V. Rajasekaran, R. Lalitha

Question Posted: