The labour budget of a company for a week is as follows: 20 skilled men at Rs.
Question:
The labour budget of a company for a week is as follows:
20 skilled men at Rs. 5 per hour for 40 hours.
40 unskilled men at Rs. 3 per hour for 40 hours.
The actual employment was as follows:
30 skilled men at Rs. 5 per hour for 40 hours.
30 unskilled men at Rs. 4 per hour for 40 hours.
Calculate labour variances.