During a period 25 600 labour hours were worked at a standard cost of 7.50 per hour.

Question:

During a period 25 600 labour hours were worked at a standard cost of £7.50 per hour. The direct labour efficiency variance was £8250 adverse. How many standard hours were produced?

A 1100. B 24500. C 25 600.

D 26700.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: