You are a project engineer assigned to calculate the cost of a repetitive activity in your project.
Question:
You are a project engineer assigned to calculate the cost of a repetitive activity in your project. A total of 25 iterations of this activity is required for the project. The activity takes 3.5 hours at its steady state and the learning rate is 70%. Calculate the initial output time required for the first unit produced, using the learning curve formula given in this chapter. Assume that the steady state is reached at n = 25.