2-47 Rose is a project manager at the civil enginee ing consulting firm of Sands, Gravel, Concrete,...

Question:

2-47 Rose is a project manager at the civil enginee ing consulting firm of Sands, Gravel, Concrete, and Waters, Inc. She has been collecting data on a projec in which concrete pillars were being constricted however not all the data are available. She has bees able to find out that the 10th pillar required 269 person-hours to construct, and that a 75% learning curve applied. She is interested in calculating the time required to construct the 1st and 20th pillan Compute the values for her.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economic Analysis

ISBN: 9780357419687

11th Edition

Authors: Donald Newnan, Ted Eschenbach, Jerome Lavelle

Question Posted: