3-36. Find the average time per unit required to produce the first 30 units, if the slope...

Question:

3-36. Find the average time per unit required to produce the first 30 units, if the slope parameter of the learning rate is 92% and the first unit takes 460 hours.

(a) 330.693

(b) 305.5404

(c) 245

(d) 347.3211

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Engineering Economy

ISBN: 9780134870069

17th Edition

Authors: William Sullivan, Elin Wicks, C Koelling

Question Posted: