5. 5.27 A new bridge across the Allegheny River in Pittsburgh is expected to be permanent and...

Question:

5. 5.27 A new bridge across the Allegheny River in Pittsburgh is expected to be permanent and will have an initial cost of $30 million. This bridge must be resurfaced every five years at a cost of $1 million. The annual inspection and operating costs are estimated to be $50,000. Determine its equivalent annual cost of this long-life construction at i = 10% per year.