A survey of total project construction costs for a wide range of buildings (hospitals, schools, banks, nursing

Question:

A survey of total project construction costs for a wide range of buildings (hospitals, schools, banks, nursing homes, etc.) in 2006 found that the average cost was $13,136,431. The mechanical and electrical portions of that cost were $2,511,893 and $1,585,384, respectively. If the total project cost in 2017 increases to $15,700,000, what would the mechanical portion of the total cost equal, provided the percentage

(a) Remained the same as in 2006,

(b) Increased by 20% from the 2006 portion?