Allison and Joshua are engineers at Raytheon. Each has presented a proposal to track fatigue development in
Question:
Allison and Joshua are engineers at Raytheon.
Each has presented a proposal to track fatigue development in composite materials installed on special-purpose aircraft. Which is the better plan economically, if i 12% per year compounded monthly?
Allison’s Plan Joshua’s Plan Initial cost, $ 40,000 60,000 Monthly M&O costs, $ per month 5,000 —
Semiannual M&O cost, $ per 6-month — 13,000 Salvage value, $ 10,000 8,000 Life, years 5 5