If the two independent projects shown are evaluated using an interest rate of 10% per year and
Question:
If the two independent projects shown are evaluated using an interest rate of 10% per year and the B/C ratio method, the decision is to:
a. select do-nothing
b. select X
c. select Y
d. select X and Y Project X Project Y Annualized first cost, $/year 60,000 90,000 Annual M&O cost, $/year 45,000 35,000 Annual benefits, $/year 110,000 150,000 Annual disbenefits, $/year 20,000 45,000 Life, years