In conducting a sensitivity analysis of a proposed project, the present worth values of $10,000, $40,000, and

Question:

In conducting a sensitivity analysis of a proposed project, the present worth values of $–10,000, $40,000, and $50,000 were believed to have chances of 25%, 40%, and 35%, respectively. The expected PW is closest to:

(a) $19,000

(b) $26,000

(c) $28,500

(d) $31,000