million gallons per day to meet increasing demand. One alternative is to spend $10 million to increase

Question:

million gallons per day to meet increasing demand. One alternative is to spend $10 million to increase the size of an existing reservoir in an environmentally acceptable way. Added annual upkeep will be $25,000 for this option. A second option is to drill new wells and provide added pipelines for transportation to treatment facilities at an initial cost of $1.5 million and annual cost of $120,000. The reservoir is expected to last indefinitely, but the productive well life is only 10 years. Compare the alternatives at 5% per year.