LO.3 Josepis construction company uses the completed contract method. During the three-year period 20122014, Josepi recognized the

Question:

LO.3 Josepi’s construction company uses the completed contract method. During the three-year period 2012–2014, Josepi recognized the following income on his two construction contracts:

Year Contract 1 Contract 2 2012 $700,000* $ –0–

2013 –0– –0–

2014 –0– 800,000**

* Construction completed in 2012.

** Construction completed in 2014.

If Josepi had used the percentage of completion method, he would have recognized the following income:
Year Contract 1 Contract 2 2012 $40,000 $275,000 2013 –0– 225,000 2014 –0– 300,000 Calculate the AMT adjustment for 2012, 2013, and 2014.