On March 15, 2007, Frankel Construction contracted to build a shopping center at a contract price of
Question:
On March 15, 2007, Frankel Construction contracted to build a shopping center at a contract price of \(\$ 120\) million. The schedule of expected (which equals actual) cash collections and contract costs follows:
a. Calculate the amount of revenue, expense, and net income for each of the three years 2007 through 2009 using the percentage-of-completion revenue recognition method.
b. Discuss whether or not the percentage-of-completion method provides a good measure of this construction company's performance under the contract.