Cleary, Inc., manufactures door panels. Suppose Cleary is considering spending the following amounts on a new total

Question:

Cleary, Inc., manufactures door panels. Suppose Cleary is considering spending the following amounts on a new total quality management (TQM) program:

image text in transcribed

Cleary expects the new program would save costs through the following:

image text in transcribed

Requirements 

1. Classify each cost as a prevention cost, an appraisal cost, an internal failure cost, or an external failure cost.

2. Should Cleary implement the new quality program? Give your reason.