16.8. The following activities are required for completing a project: a. Draw a network diagram of this
Question:
16.8. The following activities are required for completing a project:
a. Draw a network diagram of this project showing the activities and their expected duration times.
b. What is the critical path and the expected completion time of the project?
c. What is the probability of completing the project in 41 days or less?