A Cantilever Ltd was awarded a contract to build an office block in London and work commenced

Question:

A Cantilever Ltd was awarded a contract to build an office block in London and work commenced at the site on 1 May 2013.

During the period to 28 February 2014, the expenditure on the contract was as follows:

Materials issued from stores ..... 9,411 Materials purchased Direct expenses ..... 6,149 Wages ..... 18,493 Charge made by the company for administration expenses ..... 2,146 Plant and machinery purchased on 1 May 2013, for use at site ..... 12,180 On 28 February 2014, the materials at the site amounted to $£ 2,164$ and there were amounts outstanding for wages $£ 366$ and direct expenses $£ 49$.

Cantilever Ltd has received on account the sum of $£ 64,170$ which represents the amount of Certificate No. 1 issued by the architects in respect of work completed to 28 February 2014, after deducting $10 \%$ retention money.
The following relevant information is also available:

(a) the plant and machinery have an effective life of five years, with no residual value; and

(b) the company only takes credit for two-thirds of the profit on work certified.
\section*{Required:}

(a) prepare a contract account for the period to 28 February 2014; and

(b) show your calculation of the profit to be taken to profit and loss in respect of the work covered by Certificate No. 1.
(Institute of Chartered Accountants)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Frank Woods Business Accounting Volume 2

ISBN: 9780273767923

12th Edition

Authors: Frank Wood, Ph.D. Sangster, Alan

Question Posted: