Sydney Lanes, a local bowling alley, installed automatic scorekeeping equipment. The electrical work required to prepare for
Question:
Sydney Lanes, a local bowling alley, installed automatic scorekeeping equipment. The electrical work required to prepare for the installation was $18,000. The invoice price of the equipment was $180,000. Additional costs were $3,000 for delivery and $600 for insurance during transportation. During the installation, a component of the equipment was damaged because it was carelessly left on a lane and hit by the automatic lane cleaning machine. The cost of repairing the component was $2,250. What is the cost that should be capitalized of the automatic scorekeeping equipment?