Predetermined Manufacturing Overhead Rates The Boise Manufacturing Company uses a job order costing system. For Job #221,

Question:

Predetermined Manufacturing Overhead Rates The Boise Manufacturing Company uses a job order costing system. For Job #221, the production manager requisitioned $1,350 of direct materials and used 50 hours of direct labor at $19 per hour. Manufacturing overhead is applied on the basis of direct labor hours, using a predetermined overhead rate. At the beginning of the year, $956,250 of manufacturing overhead costs were estimated based on a forecast of 225,000 direct labor hours.

Prepare a summary of the costs for Job #221. (Note: You have to calculate the predetermined overhead rate.)