After estimating a projects NPV, the analyst is advised that the fixed capital outlay will be revised

Question:

After estimating a project’s NPV, the analyst is advised that the fixed capital outlay will be revised upward by $100,000. The fixed capital outlay is depreciated straight-line over an eight-year life. The tax rate is 25 percent, and the required rate of return is 10 percent. No changes in cash operating revenues, cash operating expenses, or salvage value are expected. What is the effect on the project NPV?

a. $83,328 decrease.

b. $73,325 decrease.

c. $59,988 decrease.

d. No change.