A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated financial
Question:
A city government is considering increasing the capacity of the current wastewater treatment plant. The estimated financial data for the project are as follows:
Description Data
Capital investment…………………………$1,200,000
Project life………………………….................25 years
Incremental annual benefits………………...$250,000
Incremental annual costs……………………$100,000
Salvage value…………………………...........$50,000
Discount rat………………………….......................6%
Calculate the benefit–cost ratio for this capacity expansion project.